The aim of the investment was to build and start up a plant installation of demineralized water between two plants together with a demineralized water production station, water tanks and a pumping station.
The additional function of this installation was also to use one of the pipelines for transporting hot (temperature 109°C) condensate between the two energy buildings.
As part of the investment, demineralized water and condensate 2xDN 150 pipelines with a total length of ~ 5,500 mb were built, two demi water tanks each with a capacity of 800m3, a demi water pumping station with three electric pumps and an emergency pump with a diesel engine.
The scope of our work included the Building Permit Design and detailed designs for the entire investment, including the supporting structure on the piperacks, pumping station foundations for finished tanks and electrical installations, I&C and auxiliary installations.